If 15 workers did a job is 8 hours, how long would it take 5 workers to do half of this job?

Respuesta :

mrmetsman123 mrmetsman123
  • 09-04-2017
Since 15 workers did 8 hours of work, the total amount of work needed is 120 hours. Half of this job would be 60 hours. Then divide this amount by the 5 workers doing the job. This would make the job 12 hours
Answer Link
irspow
irspow irspow
  • 09-04-2017
J=15w*8h=120(worker*hours)

5h=120/2

5h=60

h=12 hours
Answer Link

Otras preguntas

Rod is paid an overtime rate of $25 per hour after he earns his basic wage of $600 per week. Write an equation in slope-intercept form for the total pay p if h
turn this sentence into an algebraic equation: ann has 5 newest music CD's which is 3 less than twice the amount that bob has
Find the length of a degree on the equator, considering the diameter of the equator to be 7912 miles
What does it mean to describe a scientist as skeptical? Why is skepticism considered a valuable quality in a scientist
4,000 is times as much as 4
A school has 10 classes with the same number of students in each class. One day, the weather was bad and many students were absent. 5 classes were half full, 3
turn this sentence into an algebraic equation: ann has 5 newest music CD's which is 3 less than twice the amount that bob has
Round 5,890 to the nearest thousand
527,519 in expanded form using exponents
What are the special names on the globe?